Operational / process hazard identification & risk assessment (HIRA)

Task / activity Isolate and replace ground-floor consumer unit; extend ring final circuit to two new sockets in an occupied office. Works outside core hours. RA number01
CompanyNorthline Services Ltd ClientRiverside Offices Ltd SSoW number01
Site / location 14 Quay Street, Manchester M3 4AE — ground floor riser and open-plan office Date created14/09/2026
Written byA. Khan, SMSTS Approved byA. Khan, SMSTS Review14/03/2027
Job / work orderNL-882 Isolation / permitElectrical isolation permit — building manager, 14/09/2026
Who can be harmed Those doing the task [Y]   Others in vicinity [Y]   Visitors [ ]   Public [Y]
Hazard description Hazard effect S Existing control measures Additional controls to reduce risk Final risk
What and howHLRR HLRR
Electric shock / burns from live services Electricians and other trades — shock, burns, fatality 5 Safe isolation, lock-off, tag. Prove dead with GS38 voltage indicator and proving unit. Competent electrician only. H2210 Retain keys. Inform building user. No live work. Second person present for isolation. H315
Stored energy / unexpected re-energising Electricians — shock if the circuit is restored 5 Prove dead at the point of work. Lock-off kit on the device. Warning tag. H3210 Building manager briefed. Do not restore until tests complete and the team is clear. H315
Working at height (podium / steps) Operatives — falls, sprains, struck by falling tools 4 Podium or hop-up — no chairs or unstable steps. Inspect before use. Tool tethers. H228 Exclusion below. Hard hats if others pass. Stop if the podium is damaged. H314
Occupied building — staff, dust, access Office staff and visitors — trip, dust, blocked fire route 3 Works 18:00–22:00. Barriers and signage on the corridor. Dust sheets. Fire routes kept clear. H326 Brief reception. Stop if the public enter the exclusion zone. H313
Manual handling of CU and cable drums Musculoskeletal injury 3 Two-person lift for the board. Split drums. Only lift what you can. H226 Trolley from van to riser. No twisting on the podium. H413
Slips, trips and trailing leads Cuts, bruising, fractures — other trades and staff 3 Tidy as you go. Route leads around the exclusion. Non-slip footwear. H426 Clear waste before leaving each night. H413
Fire from isolation / testing / wipes Burns, smoke, property damage 4 Know alarm and assembly. Extinguisher in the work area. IPA wipes capped, no ignition sources. H428 Do not block exits. Small quantity of cleaner only. H414

H1 Eliminate · H2 Reduce · H3 Isolate · H4 Control · H5 PPE. RR = S × L. 1–4 low · 5–9 medium · 10–25 high. Retain this document for a minimum of 3 years.

Safe system of work (SSoW) / method statement

Task Consumer unit replacement and ring final extension — occupied office, out of hours Location 14 Quay Street, Manchester M3 4AE
SSoW no.01 Written byA. Khan, SMSTS Date14/09/2026
RA no.01 Approved byA. Khan, SMSTS Review14/03/2027
Isolation no. Electrical isolation permit — building manager
Non-standard PPE Permit to work Equipment needed
Safety footwear, eye protection, gloves. Flame-retardant overalls if live testing cannot be avoided (it will be avoided). See site contact / building manager. Electrical isolation permit before lock-off. GS38 voltage indicator and proving unit, lock-off kit, insulated tools, vacuum, podium, test instruments calibrated.
COSHH assessment ref.
Isopropyl alcohol / electrical cleaning wipes — SDS dated 02/2026 (attach the sheet)

Communication with other workers on site

All staff report to reception / the building manager for induction on arrival. The site contact will say what else is happening in the building. Northline will say what isolation is planned and when power will be off. Notices on the corridor. Cleaners and security briefed that the ground floor riser is a no-go until lock-off is removed.

First aid

Northline provides a trained first aider on this shift and a first aid kit in the van. The appointed person can call an ambulance. Do not touch a casualty still in contact with live parts — isolate first if it is safe. Nearest A&E as the site induction. All staff shown the kit location at the briefing.

Manual handling

Staff have been instructed on manual handling. Two-person lift for the consumer unit. Split cable. Use a trolley from the loading bay. Do not lift beyond capability. Supervisor controls handling on the night.

Material handling

Unload to the agreed drop zone, not the fire route. Keep it tidy. Collect boards and cable as needed. Stack so the pile is stable. Take waste out the same night.

Personal protective equipment (PPE)

PPE is the last line of defence. On this job: safety boots, company workwear, eye protection and gloves for installation. Hearing protection not required for this task. RPE not required if dust is vacuumed. Hard hat if other trades work above — none planned tonight.

Preparation & induction

This RAMS is briefed before lock-off. Queries go to A. Khan. Follow building rules. Other activities that could affect this task: evening cleaners — they will be told the exclusion is in force.

Competence / training

Qualified electrician, 18th Edition, ECS card. Supervisor (A. Khan) on site. No lone isolation. Testers in calibration.

Welfare

Use existing building toilets and rest area as agreed. Leave them clean. Drinking water available. No work while fatigued — this is an evening shift, plan a break.

Procedure

1Report to site contact / building manager. Confirm it is safe to set up. Sign in.
2Put on general PPE. Brief this RAMS and the isolation plan with the team.
3Inspect the work area. Report unforeseen hazards. Do not start if the office is still occupied without agreement.
4Set exclusion zone, barriers and warning signage on the corridor. Keep the fire route clear.
5Identify the circuit. Agree isolation with the building manager. Complete the permit.
6Isolate, lock off and tag. Prove the tester, prove dead at the point of work, prove the tester again (GS38).
7Daily pre-work check of tools, podium and test kit.
8Replace the consumer unit. Extend the ring final circuit to two new sockets. Install to BS 7671.
9Inspect, test and certificate. Do not restore until tests are satisfactory and the team is clear.
10Remove lock-off only when safe. Inform the building manager that supply is restored.
11Vacuum waste. Remove barriers. Leave the corridor clear.
12See site contact. Hand over certificates. Sign out. Remove PPE.

Environmental considerations

Vacuum, do not sweep, board offcuts and dust. Take waste back to the van for licensed disposal. IPA wipes: small quantity, cap the pack, no drains. Cardboard and cable offcuts segregated.

Emergency procedures

Discuss with the site contact what to follow in this building. Raise the alarm. Isolate if safe. First aider on site. Do not touch a casualty still in contact with live parts. Assembly point as induction. Report RIDDOR if the criteria are met. Nearest A&E as the site induction.

COSHH assessment

Isopropyl alcohol / electrical cleaning wipes

SDS: Manufacturer SDS dated 02/2026 — attach the current sheet to this pack.
Hazards: Highly flammable. Vapour may cause drowsiness. Irritant to eyes.
Routes: Inhalation, skin, eyes.
WEL: Check current EH40 for IPA; ventilate the room.

Controls: Small quantities only. No ignition sources. Cap wipes. Ventilate. Gloves and eye protection.

Emergency: Remove from ignition sources. Eyes: rinse. If inhaled: fresh air.

Health surveillance: Not required for this short use unless the SDS says otherwise.

Daily STOP check

DateDecisionLeadNotes
14/09/2026 17:45 GO A. Khan Office empty. Isolation agreed. Fire routes clear. Team briefed on this RAMS. All STOP boxes ticked.

Safe system of work — sign-off

I confirm that I have read, understood and will follow this Safe System of Work / method statement. I will report any deficiencies so health and safety standards can be maintained.

NameSignatureDateInducted by
A. Khan14/09/2026Self / SMSTS
J. Reid14/09/2026A. Khan

SAMPLE ONLY. Site Safety Docs drafts packs in this layout when you tap Send or Export PDF. A competent person must make the real document site-specific. Attach the current safety data sheet to any COSHH page. Risk assessments must be suitable and sufficient under the Management of Health and Safety at Work Regulations 1999. COSHH must follow the COSHH Regulations 2002. Construction work may also need to satisfy CDM 2015. Retain with the HIRA for a minimum of 3 years.